summaryrefslogtreecommitdiff
path: root/assignment1
diff options
context:
space:
mode:
authorrekado <rekado@elephly.net>2013-04-07 07:08:30 +0800
committerrekado <rekado@elephly.net>2013-04-07 07:08:30 +0800
commit0260f0f63ea1e3fbf8b24e341cf86e5feebba1cf (patch)
tree2788c463aa83a5ac3b3156365cc0e1fb78ae59db /assignment1
parent516bd4ddd4a0ffec4b97224e14cb9aeae7baf311 (diff)
spelling
Diffstat (limited to 'assignment1')
-rw-r--r--assignment1/discussion.tex18
-rw-r--r--assignment1/main.tex8
2 files changed, 13 insertions, 13 deletions
diff --git a/assignment1/discussion.tex b/assignment1/discussion.tex
index 443e539..164dad0 100644
--- a/assignment1/discussion.tex
+++ b/assignment1/discussion.tex
@@ -19,7 +19,7 @@ work \parencite{practitioners}.
% TODO: consideration of alternatives: how about the RMA?
According to a survey of EIA practitioners \parencite{practitioners},
-the lack of central guidance on impact assessment practice makes it
+the lack of central guidance on impact assessment practise makes it
difficult for the assessors---planning professionals and engineers who
are often minimally trained in EIA---to produce adequate
assessments. The guideline presented by the Fourth Schedule of the RMA
@@ -28,13 +28,13 @@ result, assessments are not seen as a means to enable affected parties
and decision makers to find a well-informed compromise that is
acceptable by all participants, although aiding decision-making
processes is a core principle of EIA; instead, a majority of survey
-participants primarily aimed to fulfill the requirements of the Fourth
+participants primarily aimed to fulfil the requirements of the Fourth
Schedule in preparing an AEE and was not concerned with following
-international EIA best practice \parencite{practitioners}.
+international EIA best practise \parencite{practitioners}.
%- failure to predict important impacts
-A review of constent processing performance by the Ministry for the
+A review of consent processing performance by the Ministry for the
Environment further revealed that councils rarely reject subpar
resource consent applications as permitted by section 88(3) of the
RMA; much more often faulty applications are accepted and gradually
@@ -60,12 +60,12 @@ well.
\subsection{Participation of the public}
Although the use of objective measurements and scientific methodology
-is considered EIA best practice \parencite{principles}, EIA is neither
+is considered EIA best practise \parencite{principles}, EIA is neither
science nor is it an objective process. As environmental impact
statements are produced by project proponents with the goal to
convince decision-makers of the benefits of the project in question,
the report is a subjective statement or even a piece of project
-advocacy \parencite{TODO}. In recognition of this inherent bias, the
+advocacy \parencite{beattie}. In recognition of this inherent bias, the
EIA process calls for the participation of the general public, in
particular the participation of affected individuals or interest
groups \parencite{wilkins}.
@@ -89,7 +89,7 @@ the resource consent level, however, is a different one. According to
the 2010/11 survey of local authorities the New Zealand
\textcite{rma-survey} carries out every two years, only about six per
cent of all resource consents in the two-year period were notified in
-some way, with only four per cent being publically notified (``poor
+some way, with only four per cent being publicly notified (``poor
provision of information''). Hence, although the public can influence
the framework relative to which resource consents are evaluated, there
is limited opportunity for the public to affect the outcome of the
@@ -152,10 +152,10 @@ been relatively slow in publishing these national
guidelines \parencite{miller2010implementing}. Although according to
\textcite{sadler}, the integrated approach to EIA encouraged by the
RMA should, in theory, be sufficient to establish a ``context and
-parameters for susidiary EIAs, which are required for all resource use
+parameters for subsidiary EIAs, which are required for all resource use
consents'', due to slow implementation of the RMA ``local governments
still rely on project EIA rather than undertaking policy and
plan-level assessments'' (p 146). The relative lack of guiding
constraints on local plans favours regional differences in the
implementation of environmental management
-practices \parencite[see case studies in][]{discussion}. \ No newline at end of file
+practises \parencite[see case studies in][]{discussion}. \ No newline at end of file
diff --git a/assignment1/main.tex b/assignment1/main.tex
index 4aaef5f..df8fa1b 100644
--- a/assignment1/main.tex
+++ b/assignment1/main.tex
@@ -20,7 +20,7 @@ In order to provide decision-makers with sufficiently detailed insight
into the potential positive and negative effects of a project on the
environment, the participation of all parties that would be affected
by the project, as well as the participation of the general public is
-explicitly encouraged \parencite{principles}. The involvment of the
+explicitly encouraged \parencite{principles}. The involvement of the
public in the decision-finding process is a crucial component of EIA
as those responsible for the project proposal and the prediction of
its impacts on the social and natural environment do not necessarily
@@ -157,9 +157,9 @@ environmental acts other than the
RMA \parencite{miller2010implementing}.}. The Ministry is supposed to
prepare and publish national policy statements---declaring governance
intent relating to issues affecting the whole country or in
-fulfillment of international agreements---as well as national
+fulfilment of international agreements---as well as national
environmental standards (specific points of reference in the areas of
-air quality, water quality, etc).
+air quality, water quality, etc.).
According to \textcite{furuseth}, ``among local government units, the
regional councils are presented with the greatest responsibilities and
@@ -201,7 +201,7 @@ council that received the resource consent application may decide to
involve the public by means of public notification or determine that
public notification is not required when the activity is expected to
only have minor effects and all affected parties agree on the
-proposal \parencite{fookes}. When an application is publically
+proposal \parencite{fookes}. When an application is publicly
notified, the application is to be reviewed under consideration of
public submissions and the results of public hearings. Participants in
the public submission and hearing steps may also appeal to the